Repairs · Insight·24 September 2024·5 min read

Cracked sea water line at berth: the overnight repair sequence, step by step

A specific defect, a specific night, and the sequence that closes it before the morning watch — with class in the loop the whole way.

A cracked sea water line found on a routine watch inspection at 20:30. Vessel scheduled to sail at 08:00. Below is the sequence we run for exactly this failure.

The defect

Circa 200 mm circumferential crack on a 4" sea water suction line to a main engine cooler, isolatable at both ends. Corroded, thinned original pipe, dry inside the isolated section.

20:45 — attendance and containment

On board within 30 minutes of the call. Chief Engineer confirms isolation is intact and the line can stay drained overnight. Class notified — surveyor available for morning attendance.

21:10 — scope agreed

Crop the affected section: approximately 800 mm, valve to elbow. Fabricate insert pipe in the workshop from a spec-matched stock length. WPS on file, welder certified, consumables logged.

21:40 — measurements and preparation

Exact lengths and angles taken. Pipe spool cut, bevelled and dry-fitted in the workshop. Photo of the marked-up spool with the vessel and defect number.

23:15 — cropping on board

Hot work permit signed, fire watch briefed. Cropped section removed. Edges cleaned and prepared for welding.

00:30 — root pass and fill

Root pass welded on the first joint. NDT-friendly technique — no lack of penetration. Fill and cap passes.

02:45 — second joint

Same sequence on the elbow-side joint. Photos between each pass for the report.

04:15 — hydrotest

System re-filled and pressure tested to 1.5 × working pressure. Held for 30 minutes. No weep.

06:00 — class attendance

Surveyor on board with the class file open. Visual and NDT on both welds. Accepted. Certificate updated on the spot.

07:30 — clean and clear

Site cleaned, PMS updated, repair report signed and handed to the Chief Engineer.

08:00 — pilot on board

Vessel sails on time.

What made it close overnight

A welder available and awake at 22:00. A pipe stock the right spec on the shelf. A class file that was ready before the survey was asked for. No heroics — a process.

If you have a piping or plating defect that must close before morning, call the line. We are staffed for exactly this shift.